Framing Inspection in Ontario: What Inspectors Check, When to Book It, and a Complete Checklist

Framing Inspection in Ontario

Last updated: November 23, 2026. Checked against the 2024 Ontario Building Code (O. Reg. 163/24) and inspection guidance from the City of Toronto, Mississauga, Brampton, Oakville, Vaughan, Barrie and the Electrical Safety Authority (ESA).

Quick answer: A framing inspection is a mandatory visit from a municipal building inspector once the structure of your building is complete, but before insulation or drywall covers it. The inspector checks that the framing matches your approved permit drawings and the Ontario Building Code, so the loads from the roof travel safely down through the walls and floors to the foundation. In most Ontario cities, plumbing and HVAC rough-ins must already be in place (and often passed) before you book it. Nothing gets insulated until the framing passes.

Key takeaways

  • It's the law, not a courtesy. The Ontario Building Code requires the builder to tell the city when the work is ready for each mandatory inspection.

  • Timing matters more than anything. Book it when all framing is done and rough-ins are in, but before a single batt of insulation goes up.

  • Electrical is a separate inspection in Ontario. The Electrical Safety Authority (ESA), not the city, inspects wiring. Most cities still expect electrical rough-in to be done before framing is booked.

  • Each city has its own small rules. Oakville wants the house weather-tight. Brampton wants rough-ins passed first. Check your permit card.

  • Use Canadian sources only. US framing inspection guides follow a different code and a different inspection system.

  • The inspection itself usually costs nothing extra. In Toronto it's included in your permit fee. The real cost of a failed inspection is delay and rework.

What Is a Framing Inspection?

A framing inspection is the city's check of your building's skeleton: the studs, joists, beams, posts, headers, trusses and sheathing that hold everything up.

Once the frame is up and before it disappears behind insulation and drywall, a provincially qualified building inspector walks the job. They compare what's built to two things:

  1. Your approved permit drawings (the stamped set the city reviewed)

  2. The Ontario Building Code (OBC), which since January 1, 2025 is the 2024 edition, O. Reg. 163/24

The goal is simple. The inspector confirms that the weight of the building, plus snow, wind and the people inside, can travel from the roof, through the walls and floors, down to the foundation without a weak link along the way. Builders call this the load path.

Who it's for: anyone with a building permit for a new house, addition, basement finish, multiplex, garden or laneway suite, garage, or commercial build-out with framing.

Other names you'll hear: structural framing inspection, rough framing inspection, house framing inspection, or building framing inspection. In Ontario they all mean the same stage.

Key points

  • It's a mandatory stage under the Ontario Building Code.

  • It happens after framing, before insulation.

  • The inspector checks the frame against your drawings and the code.

Why Ontario Framing Inspections Are Different From US Guides

Most "framing inspection checklist" templates online are written for US codes. Ontario builds to a different code, with a different inspection system, so a US checklist can send you to the wrong inspection at the wrong time.

Here's what changes when you're building in Ontario:

Category Ontario Typical US Guide
Code Ontario Building Code (2024), based on the National Building Code of Canada 2020 International Residential Code (IRC) or International Building Code (IBC)
Houses and Small Buildings Part 9 of the OBC IRC
Electrical Inspection Separate authority: the Electrical Safety Authority (ESA) Often done by the same city inspector, sometimes combined with framing
Units Metric, with Canadian lumber grades and span tables Imperial
Climate Details Separate insulation and vapour barrier inspection after framing; air barrier and fire stopping checked closely Varies by state
Who Books It The permit holder notifies the Chief Building Official at each stage Varies by county

In plain terms: if you follow a US checklist, you might wait for an "MEP and framing combo" inspection that doesn't exist here, or forget that the ESA has to see your wiring before anything is covered.

When to Call for a Framing Inspection

Call for your framing inspection when every structural member is in place and the plumbing and HVAC rough-ins are done, but before any insulation, vapour barrier or drywall goes up.

Here's the usual order on an Ontario house:

  1. Footings and foundation inspected and passed

  2. Framing complete: walls, floors, roof, trusses, stairs, sheathing, headers, beams and posts

  3. Rough-ins installed: plumbing (drains, waste, vents, water lines), HVAC ductwork and electrical wiring

  4. ESA electrical rough-in inspection (booked by your licensed electrician)

  5. City framing inspection (often done on the same visit as the plumbing and HVAC rough-in inspections)

  6. Fire separation inspection where your project has rated walls or floors

  7. Insulation and vapour barrier inspection

  8. Drywall, finishes, then final inspection to close the permit

On bigger buildings, the timing changes. In Toronto, large or complex buildings (Part 3 of the code) get a structural framing inspection at the completion of each storey, not once for the whole building.

How to book in Toronto: permit holders use the Toronto Building inspection request portal, and inspections happen within two business days of the date you request. Keep the stamped permit plans on site. The inspector must be able to see the whole element being inspected.

Our tip: do your own walk-through the day before you book. If anything isn't ready, it's cheaper to move the inspection than to fail it.

Framing Inspection Requirements Across the GTA

Every Ontario city follows the same Building Code, but each one words its "ready for framing inspection" rules a little differently. Always follow the list on your own permit card.

City What Must Be Done Before You Book Framing
Toronto (houses and small buildings) Structural framing complete, including plumbing and HVAC rough-in
Toronto (large buildings) Inspected at completion of structural framing for each storey
Mississauga All framing and electrical work complete; plumbing, electrical and HVAC rough-ins done and passed; no insulation installed; fire blocks and firestopping in place
Brampton (basements, additions, interior alterations) HVAC and plumbing rough-ins completed and passed by the inspector first
Oakville House must be weather-tight (exterior cladding or wrapped with membrane)
Vaughan (small commercial buildings) Structural framing complete; fire blocking at floor levels done; plumbing, electrical and HVAC ductwork passed first
Barrie Electrical, windows, shingles, HVAC and plumbing rough-in complete; all joists, headers, trimmers, studs and posts installed

If you're building outside Toronto, don't assume Toronto's list applies. Your inspector's name and your required inspections are usually printed on the permit card or available in your city's online permit portal.

What Do Framing Inspectors Look For?

Framing inspectors look at how loads move through the building and whether every structural piece matches the approved drawings. Most failed inspections come down to a handful of repeat issues.

Ontario municipal framing guides (like those from Kenora, Kapuskasing and Grimsby) list the main areas inspectors review:

Structure and load path

  • Columns, posts and beams: right size, right material, sitting on proper footings

  • Floor joists, rafters and beams: correct size, spacing and span

  • Headers and lintels over doors and windows

  • Point loads carried all the way down, with solid blocking (squash blocks) through floors

  • Engineered products like LVL beams, I-joists and trusses installed to the manufacturer's specs

Connections

  • Joist hangers installed, with every nail hole filled as specified

  • Sheathing and wall bracing nailed to the required pattern

  • Anchorage of the frame to the foundation (anchor bolts, sill plates)

  • Wood walls sitting on steel beams mechanically fastened to the beam

Roof and trusses

  • Sealed truss drawings on site (many cities ask for these)

  • Truss bracing and bottom chord bracing installed

  • No cut or modified trusses without an engineer's repair detail

Holes, notches and cuts

  • Plumbers, electricians and HVAC trades can weaken framing when they drill or notch. Inspectors check that cuts stay within code limits, especially in I-joists and load-bearing studs. (Not sure which walls are load-bearing? Read our guide to load-bearing walls.)

Fire safety

  • Fire blocking in concealed spaces, like wall cavities and between floors

  • Fire separations ready for firestopping where the drawings call for them

  • On party walls, joists on each side staggered and fire cut

Stairs, guards and openings

  • Stair framing that matches the drawings (rise, run, headroom, width)

  • Rough openings sized for windows and doors, plumb and square

Drawings

  • What's built matches the approved permit drawings. If something changed on site, the change needs to be approved before the inspection.

Want to see the mistakes that trip up most jobs? We break them down one by one in 10 Common Framing Mistakes That Fail Inspections in Toronto and the GTA.

Inspector checking joist hangers and beam bearing on a wood-framed house

Framing Inspection in Ontario

Framing Inspection Checklist for Ontario Homes

Use this residential framing inspection checklist the day before your inspection. It doesn't replace your inspector, but it catches the common misses while they're still cheap to fix.

Framing Inspection Checklist
0 of 34 items completed

1. Paperwork and Site

2. Walls

3. Floors, Beams and Posts

4. Roof Framing

5. Openings, Stairs and Guards

6. Fire Safety

7. Other Trades

8. Final Step

📄 Download the printable Ontario Framing Inspection Checklist (PDF): two pages with space for your permit number, inspection date and notes. Print it and walk it with your framer the day before your inspection.

Tip for Tatiana's team and owners: print this list and walk it with your framer. If something looks structurally wrong, like a sagging beam or a cracked joist, don't wait for the inspector. Call your framer or engineer right away.

Ontario Framing Inspection Checklist Infographic.webp

Basement Framing Inspection Checklist

A basement finish needs a building permit in Ontario, and the framing inspection usually comes after the plumbing and HVAC rough-ins pass, but before insulation and vapour barrier.

Brampton's mandatory inspections for basement finishes give a good example of the usual order:

  1. Underground plumbing

  2. Aboveground plumbing rough-in

  3. HVAC rough-in and basement ductwork

  4. Structural framing (rough-ins must already be passed)

  5. Insulation and vapour barrier

  6. Final inspection

Extra basement items to check before you book:

Additional Framing Checks

Planning a legal basement apartment? Our basement framing team frames finished basements and secondary suites to the drawings and the inspection sequence, so you aren't tearing out work later.

Commercial Framing Inspections and Partition Walls

Commercial projects in Ontario still get framing inspections, but larger buildings follow Part 3 of the Building Code, with inspections per storey and separate fire separation inspections. Office partition walls are usually inspected if they're part of your permit, especially when they're fire-rated.

What's different on commercial and larger multi-unit jobs:

  • Per-storey inspections. In Toronto, Part 3 buildings get a structural framing inspection at the completion of each storey.

  • Fire separations get their own visit. In Toronto, fire separations and closures are inspected at completion of framing for wall, floor and shaft separations, including fire stopping, before interior finishes.

  • Steel stud framing is common. Fire-rated steel stud walls have to be built exactly like the tested design on the drawings: stud size, spacing, board layers and fasteners.

  • Fire blocking at every floor. Vaughan's small commercial building inspections list fire blocking at floor levels as part of the structural framing inspection.

Do partition walls in an office need a framing inspection? If the fit-out has a building permit, your inspection list covers the work in that permit. Non-structural partitions are often reviewed at the fire separation or framing stage, especially if they're rated walls, corridor walls or demising walls between tenants. Ask your inspector at the start, because it varies with the project.

How CanaStruct helps: our commercial framing and steel stud framing crews build rated partitions, demising walls and mezzanines to the tested assemblies, and our drywall team closes them in after the inspections pass. One contractor means one schedule for framing, inspections and board.

Can You Install Windows Before the Framing Inspection? And What About Electrical?

Yes. In most Ontario cities, windows and exterior doors should already be installed when you book the framing inspection, and electrical rough-in should be done too.

Windows:

  • Brantford books framing when the roof is shingled and the windows are installed, before insulation.

  • Barrie lists windows and shingles as complete before framing.

  • Oakville asks for the house to be weather-tight.

Does the framing inspection check window installation? The framing inspector looks at the structure around the window: the header, the rough opening and the support. The air barrier and sealing around windows are usually checked at a later stage. In Barrie, for example, the air barrier inspection checks that penetrations like doors and windows are taped and sealed.

Electrical (framing inspection before or after electrical?): In Ontario, the city doesn't inspect wiring. The ESA does. The ESA rough-in inspection happens when all branch circuit wiring and outlet boxes are installed and before anything is covered by insulation, vapour barrier or drywall.

So in practice:

  • Electrical rough-in goes in before the framing inspection. Mississauga asks you to book framing once all framing and electrical work is complete.

  • Nothing gets insulated until both the city and the ESA have signed off.

  • Your licensed electrician books the ESA inspection. Ask for written confirmation it passed before you book the insulation crew.

How Much Does a Framing Inspection Cost?

The city framing inspection usually doesn't cost extra. In Toronto, mandatory inspections are included in your building permit fee. What costs money is getting ready, and fixing anything that fails.

Here's a general picture, so you know what to budget for:

Item Typical Range Notes
City Framing Inspection Included in the permit fee Toronto; other cities are similar, but check re-inspection fees
Independent Pre-Drywall Inspection (Optional) Roughly $340 to $500 Some owners and buyers hire one for a second opinion
Engineer's Site Visit for a Structural Question Several hundred to over $1,000 Depends on the firm and the issue
Fixing a Failed Item From a few hundred to several thousand dollars Depends on what's wrong and whether walls are already closed

The cost that really hurts is delay. A failed framing inspection stops insulation, drywall and every trade after them until it's fixed and re-inspected. On a tight schedule, that can mean days or weeks.

Every project is different, so we don't publish fixed prices. The size of the building, the drawings, the number of storeys and the city all change the numbers. For a clear price on your framing, including the inspection prep, request a free quote. For a better idea of what drives framing prices in general, see our guide to the cost of structural framing.

What Happens If You Fail a Framing Inspection?

If you fail, the inspector lists the deficiencies, and you fix them and book a re-inspection. You can't insulate or drywall over the failed work until it passes.

The usual steps:

  1. The inspector gives you a list of deficiencies, usually on a field inspection report.

  2. You fix each item. Some fixes need an engineer's letter, like a cut truss or an undersized beam.

  3. You book a re-inspection.

  4. Once it passes, you move to the next inspection, usually insulation and vapour barrier.

Don't cover failed work. If the inspector can't see the work, you'll be asked to open it up again. Oakville's guidance is clear: if the work can't be inspected, you'll have to uncover it.

Skipping inspections is a bigger problem than failing one. Greater Sudbury warns that failing to call for required inspections can mean exposing the work later and even prosecution under the Building Code Act. And in Toronto, an open permit can complicate selling the home later.

For the 10 issues we see most often and how to avoid each one, read 10 Common Framing Mistakes That Fail Inspections in Toronto and the GTA.

Should You Pay Your Framer After the Framing Inspection?

Many owners and builders tie a progress payment to a passed framing inspection. It's a fair, clear milestone. In Ontario, you also hold back 10% of each payment under the Construction Act.

A few things to know (this is general information, not legal advice):

  • A passed inspection is a sensible milestone. It proves the work meets the code and the drawings, which is a fair point to release a framing payment.

  • The 10% holdback is the law. Ontario's Construction Act defines the holdback as 10% of the value of the services or materials supplied. It protects everyone in the payment chain.

  • Put it in the contract. Write the payment schedule, the milestones and who fixes inspection deficiencies into your framing contract before work starts.

  • Ontario has prompt payment rules with deadlines once a proper invoice is given. Talk to a construction lawyer if you're unsure.

A good framer won't mind this arrangement. It's how we prefer to work, because it keeps everyone focused on passing the first time.

How CanaStruct Prepares Every Job for Inspection

We frame to pass the first time. That means building from the approved drawings, checking our own work before the inspector does, and coordinating with the trades that drill through our framing.

CanaStruct is led by Zura Mirzikashvili, an HCRA-licensed builder who has been framing since 2011. Here's how our crews prepare for a framing inspection:

  1. Read the drawings for inspection items first. Point loads, beams, hangers, fire blocking and rated walls are flagged before material is ordered.

  2. Keep the paperwork on site. Stamped drawings, truss drawings and engineered layouts are on site before the inspector arrives.

  3. Walk it twice. Once when framing is done, and again after plumbing, HVAC and electrical have drilled through the frame.

  4. Fix before we book. If our walk finds a miss, we fix it before the inspection, not after.

  5. Photograph everything before insulation, so you have a record of what's behind the walls.

  6. Stay on site for the inspection when needed, so questions get answered on the spot.

Whether you're building a custom home, a fourplex or multiplex, a garden suite or laneway house, or a commercial space, we build the frame the inspector expects to see.

CanaStruct crew framing a house in the GTA before the framing inspection

Frequently Asked Questions

What is a framing inspection?

A framing inspection is a mandatory building inspection in Ontario that happens after the structural framing is complete and before insulation and drywall. A municipal building inspector checks that the framing matches the approved permit drawings and the Ontario Building Code, so loads travel safely from the roof to the foundation.

What does a framing inspection consist of?

The inspector checks the main structural parts: posts, beams, joists, rafters, trusses, headers, studs and sheathing. They also check connections like joist hangers and anchors, holes and notches cut by other trades, stairs, fire blocking, and that everything matches the approved drawings.

When should I call for a rough framing inspection?

Call when all structural framing is complete and the plumbing and HVAC rough-ins are in place, but before any insulation, vapour barrier or drywall is installed. Many Ontario cities also want the rough-ins passed and the electrical rough-in done first. Check the list on your permit card.

Can you install windows before the framing inspection?

Yes. In most Ontario cities, windows and exterior doors should be installed before the framing inspection. Brantford and Barrie list windows as complete before framing, and Oakville requires the house to be weather-tight.

Is the framing inspection done before or after electrical?

In Ontario, electrical rough-in usually goes in before the framing inspection. Electrical work is inspected separately by the Electrical Safety Authority (ESA), not the city. Nothing can be covered with insulation or drywall until both inspections pass.

How much does a framing inspection cost in Ontario?

In Toronto, mandatory building inspections are included in the building permit fee, and most Ontario cities work the same way. Some cities charge for re-inspections. An optional independent pre-drywall inspection is roughly $340 to $500.

Do commercial partition walls need a framing inspection?

If the work is under a building permit, the inspections on that permit apply. Fire-rated partitions, corridor walls and walls between tenants are usually checked at the framing or fire separation stage. Ask your inspector at the start of the project.

What is a framing inspection for a garage?

A garage framing inspection checks the same structure as a house: walls, headers over the garage door, roof framing or trusses, and anchorage. For an attached garage, the inspector also checks the wall and ceiling between the garage and the house, which must keep exhaust fumes out of the home.

What happens if you fail a framing inspection?

The inspector lists the deficiencies. You fix them, book a re-inspection, and move on once it passes. You can't insulate or drywall over failed work.

Should you pay your framer after the framing inspection?

Many owners tie a progress payment to a passed framing inspection. In Ontario, you must also hold back 10% of each payment under the Construction Act. Put the payment schedule and milestones in your contract before work starts.

Frame It Right the First Time, With a Crew That Knows Ontario Inspections

A framing inspection shouldn't be a surprise. With the right framer, it's a quick visit and a signature. CanaStruct frames homes, basements, multiplexes and commercial spaces across Toronto and the GTA, led by an HCRA-licensed builder framing since 2011. We build from your approved drawings, walk the job before the inspector does, and coordinate with your trades so the frame passes and your schedule keeps moving. Send us your drawings before framing starts. That's when inspection details are easiest and cheapest to get right. Call (647) 641-0550 or request your free framing quote, and let's get your project to the next stage.

Zura

Zura is a Licensed HCRA Builder & Vendor and the Owner & Framer at CanaStruct, where he leads a framing and construction crew drawing on experience since 2011

Through the CanaStruct blogs, he shares that hands-on expertise with both homeowners and industry professionals alike.